GAOLAN PORT DUOYONGTU JETTY PHASE II PROJECT IN ZHUHAI LATEST NEWS

2011-10-01

Project Introduction:

This project was constructed by CCCC Four Harbor Consultants Co,. Ltd. The total amount is 380 million, the construction day is 655.


This project have three 5000T Multi-purpose berths, the coast line is 505m, with high-pile pier beam-slab structure. In this project, PHC 1000mm B-130 piles were manufacture by Sunway Spun Pile (Zhuhai) Co., Ltd. The single length is from 48m to 54m.This project goes smoothly right now. The implementation of the project, Zhuhai, Hong Kong will further enhance the capacity of containers and general cargo handling, port of Zhuhai hinterland laid a solid foundation of economic development.